Late Summer 2026 Progress Update #5

October: Claribel Road closes, and the first bridge deck is complete

Claribel Road closed to allow construction of the new alignment, and the left bridge reached a major milestone.

On Sunday, October 11, Claribel Road closed between Roselle Avenue and Claus Road so crews can build the new Claribel Road alignment. Detours use Oakdale, Patterson, Claus, and Sylvan. The current Claribel Road will not reopen in its present form. The new Claribel Road is expected to open around April 2027, though this may change. Nearby residents received mailers and updates in the weeks before the closure.

Bridge work also reached a milestone. Crews completed the left bridge deck and finished post-tensioning, a process that uses tensioned steel cables to strengthen the deck. Work on the right bridge is progressing through the same steps. Elsewhere, crews are monitoring the completed retaining walls as the soil behind them settles, and concrete girders for the MID bridge continue to be cast off-site.

September: An overnight pour and progress on every structure

A large concrete pour for the bridge took place overnight, and work moved ahead across the whole corridor.

On Thursday, September 17, Roselle Avenue closed between the church and Plainview at 6:30 PM for a large bridge concrete pour. The pour was expected to take approximately 16 hours and require more than 130 concrete trucks. A pour like this has to run without stopping, so the road was closed to keep crews, drivers, and emergency vehicles safe. Roselle Avenue reopened by 6:00 AM on Friday, September 18.

Work continued on every front. On the left bridge, crews began placing steel rebar to reinforce the deck. On the right bridge, crews removed the forms from the stems and started forming the deck. Along the expressway, drainage work began, and crews kept building the footings, abutments, and columns that will support the new structures. Retaining wall panels continued to be cast, and utility companies kept relocating lines along the corridor.

August: Roselle Avenue reopens

Roselle Avenue reopened to traffic ahead of the original date, while bridge construction continued alongside it.

On Monday, August 17, Roselle Avenue reopened with one lane in each direction. Drivers should expect a stop sign at Plainview and follow the posted signs.

While traffic moved through, crews kept building the two new Roselle Avenue bridges. On the left bridge, crews formed the deck, which is the road surface of the bridge, into early September. On the right bridge, they continued forming the stems, the vertical walls that support the deck.

July 2026 Progress Update #4

Construction on the North County Corridor Project continues to make strong progress! Aerial photos from July 29, 2026 show crews advancing structural work at the Claribel Road undercrossing, with rebar cages and formwork now in place for bridge walls and box girder sections ahead of upcoming concrete pours. Reinforcement work is well underway at multiple structure locations along the corridor, building on the bridge progress captured in earlier updates. Alongside the structural work, roadway grading continues to take shape, with the future expressway alignment increasingly visible across the site.

With reinforcement and formwork advancing on the bridge structures and roadway grading progressing in parallel, the project remains on track as it moves through this next phase of construction.

May 2026 Progress Update #3

Construction on the North County Corridor Project is making great progress! Aerial photos from May 5, 2026 show bridge structures rising at multiple locations along the route, with crews actively forming and pouring concrete for bridge decks, columns, and bent caps. Roadway grading and embankment work is also well underway, with the future expressway alignment now clearly visible across the landscape.

January 2026 Progress Update #2

Construction is moving forward at several locations along the route. Crews are currently building bridge foundations and columns at Roselle Avenue and Claribel Road, pouring concrete and installing support structures. In the coming weeks, work will continue on the bridges, roadway grading, and installing new irrigation and utility lines.

November 10, 2025 Progress Update #1

October 16, 2025 Groundbreaking Ceremony

May 2026 Progress Update #3

Construction on the North County Corridor Project is making great progress! Aerial photos from May 5, 2026 show bridge structures rising at multiple locations along the route, with crews actively forming and pouring concrete for bridge decks, columns, and bent caps. Roadway grading and embankment work is also well underway, with the future expressway alignment now clearly visible across the landscape.

January 2026 Progress Update #2

Construction is moving forward at several locations along the route. Crews are currently building bridge foundations and columns at Roselle Avenue and Claribel Road, pouring concrete and installing support structures. In the coming weeks, work will continue on the bridges, roadway grading, and installing new irrigation and utility lines.

November 10, 2025 Progress Update #1

October 16, 2025 Groundbreaking Ceremony

May 2026 Progress Update #3

Construction on the North County Corridor Project is making great progress! Aerial photos from May 5, 2026 show bridge structures rising at multiple locations along the route, with crews actively forming and pouring concrete for bridge decks, columns, and bent caps. Roadway grading and embankment work is also well underway, with the future expressway alignment now clearly visible across the landscape.

January 2026 Progress Update #2

Construction is moving forward at several locations along the route. Crews are currently building bridge foundations and columns at Roselle Avenue and Claribel Road, pouring concrete and installing support structures. In the coming weeks, work will continue on the bridges, roadway grading, and installing new irrigation and utility lines.

November 10, 2025 Progress Update #1

October 16, 2025 Groundbreaking Ceremony